Review 7 Buildershield Way - Electrician - Power point / GPO installation SWMS

Review the SWMS information below before signing this SWMS. If you see any issues or require clarifcation, please contact James | 0466744297 | james_webster@worksafe.vic.gov.au.

Work details

Site / work area
7 Buildershield Way
Trade
Electrician
Task
Power point / GPO installation
HRCW category
  • The area has energised electrical installations or services

Responsible person

Identified hazards and risks

  • Electric shock from contact with live wires in wall
  • Hitting existing cables or pipes when cutting into wall

Risk control measures

  • Isolate circuit and test dead before cutting into wall
  • Use cable detector to locate existing services

How controls will be implemented

  • Verify isolation before each cut
  • Scan wall with detector and mark existing services